Merrywalks Bridge Bulletin No. 26

Merrywalks Bridge Bulletin No.26  An Update from Nigel Edgeworth Work this week has mainly concentrated on the placing of steel and shuttering for the south wall of the bridge. It is anticipated that all shuttering will be in place ready for a concrete pour first thing on Monday morning. There are still some sections of the […]

Merrywalks Bridge Bulletin No. 25

Merrywalks Bridge Bulletin No.25  An update from Nigel Edgeworth  Most of the north wall has now been completed with the concrete pour having taken place on Monday 18th October. This week, steel fixers have been working on placing the reinforcing steel for the south wall of the bridge. See picture right. A concrete pour is […]

Merrywalks Bridge Bulletin No. 25

Merrywalks Bridge Bulletin No.25  An update from Nigel Edgeworth  Most of the north wall has now been completed with the concrete pour having taken place on Monday 18th October. This week, steel fixers have been working on placing the reinforcing steel for the south wall of the bridge. See picture right. A concrete pour is […]