Merrywalks Bridge Bulletin No. 30

Merrywalks Bridge Bulletin No.30

Concrete was poured on Friday 19th November. This completes the Slad Brook Culvert Headwall up to what will be the finished footway level.

This week steel fixing has been completed on the South West wall along with the shutters.

 

 

 

 

 

 

 

 

 

 

 

 

 

We hope to pour concrete later today, 26th November, although temperatures may delay this activity, current site temperature is -4oC. 

Steel fixing has also been progressed on the North West wall which will hopefully be poured by the end of next week.