Merrywalks Bridge Bulletin No.29

Merrywalks Bridge Bulletin No.29 – An Update from Nigel Edgeworth

Following the flooding experienced last week, the pumping capacity has been increased and all is now under control. 

This week has seen the completion of the bridge base.

Steel fixing has continued on the final section of the south wall and also for the concrete wall between the canal and towpath. Pictured right.

Reinforcing steel is now in place a for the Slad Brook headwall. 

The picture below shows shuttering is in place. 

A concrete pour will be completed shortly.

 

 

 

 

 

 

 

 

 

 

 

 

Click on the icon below for more details