Merrywalks Bridge Bulletin No.32

Merrywalks Bridge Update No. 32

The extreme cold continued at the beginning of the week, however, we are now enjoying some much needed warmer temperatures.

The concrete was poured for the North West wall on Tuesday 9th.

This has now completed both bridge walls.

In addition the last section of the towpath wall inside the bridge box has been poured.

Scaffolding is now being erected for the bridge deck formwork.

 

Temporary works are continuing at Slad Brook. The Contractor has installed a single pipe to carry the water away from the culvert.

It will be seen from the photo on the left that this now allows access to the piled wall adjacent to Slad Brook Culvert.

Structural concrete and brickwork facing works can now be carried out.

 

Click on the icon below to find out more about the Merrywalks Bridge Project