Cerney Wick Dredging @ An update

Cerney Wick Dredging – An update from Mike Hynd and John Maxted The dredging of the canal bed from Spine Road to Cerney Wick Roundhouse, begun by CCT volunteers in early September, has had a recent boost.  Gardiners Construction of Eastcombe near Stroud have very generously provided men and machines to level and profile the offside […]

Merrywalks Bridge Bulletin No.33

Merrywalks Bridge Bulletin No. 33 from Nigel Edgeworth Slad Brook culvert temporary works are now complete. This is comprised of temporary pipe to carry the flow of water from the culvert to the canal. See photo below. We have managed to get a good seal on the pipe where it connects into the culvert. We […]

Merrywalks Bridge Bulletin No.32

Merrywalks Bridge Update No. 32 The extreme cold continued at the beginning of the week, however, we are now enjoying some much needed warmer temperatures. The concrete was poured for the North West wall on Tuesday 9th. This has now completed both bridge walls. In addition the last section of the towpath wall inside the bridge […]