Merrywalks Bridge Bulletin No.29

Merrywalks Bridge Bulletin No.29 – An Update from Nigel Edgeworth Following the flooding experienced last week, the pumping capacity has been increased and all is now under control.  This week has seen the completion of the bridge base. Steel fixing has continued on the final section of the south wall and also for the concrete […]

Merrywalks Bridge Bulletin No. 28

Merrywalks Bridge Bulletin No. 28 – An Update from Nigel Edgeworth Site Flooded Monday saw a bad start to the week when the works became flooded following heavy rain over the weekend.  The water level had reached a depth of approximately 2m.  The contractor brought additional pumps in on Monday to drain the area. Tuesday […]

Merrywalks Bridge Bulletin No. 27

Merrywalks Bridge Bulletin No. 27. An Update from Nigel Edgeworth Three quarters of the bridge base slab and side walls are complete. Work has now started to complete the remaining section of base slab and side walls. It was not possible to complete the base and side walls in one go as space was needed […]