Merrywalks Bridge Bulletin No. 26

Merrywalks Bridge Bulletin No.26  An Update from Nigel Edgeworth Work this week has mainly concentrated on the placing of steel and shuttering for the south wall of the bridge. It is anticipated that all shuttering will be in place ready for a concrete pour first thing on Monday morning. There are still some sections of the […]

Merrywalks Bridge Bulletin No. 25

Merrywalks Bridge Bulletin No.25  An update from Nigel Edgeworth  Most of the north wall has now been completed with the concrete pour having taken place on Monday 18th October. This week, steel fixers have been working on placing the reinforcing steel for the south wall of the bridge. See picture right. A concrete pour is […]

Merrywalks Bridge Bulletin No. 25

Merrywalks Bridge Bulletin No.25  An update from Nigel Edgeworth  Most of the north wall has now been completed with the concrete pour having taken place on Monday 18th October. This week, steel fixers have been working on placing the reinforcing steel for the south wall of the bridge. See picture right. A concrete pour is […]

Merrywalks Bridge Bulletin 24

Merrywalks Bridge Bulletin No.24An update from Nigel Edgeworth This week work has concentrated on the placing of steel reinforcing for the north wall of the bridge. The contractor has been using a long reach crane to lower shuttering into position to hold the concrete in place whilst it cures. The contractor will be working throughout the […]

Merrywalks Bridge Bulletin 24

Merrywalks Bridge Bulletin No.24An update from Nigel Edgeworth This week work has concentrated on the placing of steel reinforcing for the north wall of the bridge. The contractor has been using a long reach crane to lower shuttering into position to hold the concrete in place whilst it cures. The contractor will be working throughout the […]

Merrywalks Bridge Bulletin 23

Merrywalks Bridge Bulletin 23 An Update from Nigel Edgeworth Most of the bridge base has now been cast after a difficult start on Monday morning. It was hoped to have the first concrete pour in the morning, but it took until midday before the area was pumped clear of water! Steel reinforcing is now in place […]